A critical activity is________________.a. an activity that consumes no time but shows precedence between events. b. a milestone accomplishment within the project. c. an activity with zero slack. d/ the beginning of an event.

Respuesta :

Ritmeks
Ritmeks Ritmeks
  • 09-03-2020

Answer:

C

Explanation:

Critical activity is the sequential activities from beginning to the end of a project. A lot of projects have a single critical path, although some projects may have more than one critical activity which depends on the flow logic utilized in the project.

Answer Link

Otras preguntas

2. In the troposphere, as altitude increases, air temperature drops at a relatively uniform rate. At the top of the troposphere, an average depth of 11 km, th
A persuasive essay attempts to change, or persuade, a reader's point of view on a topic. 1) Write a persuasive essay on the following prompt: Public schools
(x-2)-(3x+5) simplify
Which example provides the most complete description of an object's motion? 1. The ballerina rotated 10 times in 2 minutes. 2. Bobby threw a Frisbee 10 m throug
Why were the shinto and buddhism important to the development of japanese culture?
Does israel operates as a oligarchy?
Which poetic element help performers memorize an epic poem?check all that apply. •Rhyme •Description •List of events •Rhythm •Repetition
complete the sentence with the correct Spanish phrase; would you like me to tell you_?
Who was ammainus marcellinus
which element contains a full 2p orbital in its valence shell